File #: 055-2025    Version: 1
Type: Consent Calendar Status: Passed
File created: 2/6/2025 In control: CITY COUNCIL OF THE CITY OF NAPA
On agenda: 4/15/2025 Final action: 4/15/2025
Title: Emergency Declaration for 36-inch Asbestos Cement Water Transmission Main Replacement

To:                     Honorable Mayor and Members of City Council

 

From:                     Joy Eldredge, Utilities Director

 

Prepared By:                     Chris Jones, Senior Civil Engineer

                                          

TITLE:

Title

Emergency Declaration for 36-inch Asbestos Cement Water Transmission Main Replacement

 

LABEL

RECOMMENDED ACTION:
Recommendation

 

Determine there is a need to continue the emergency action to execute and implement contracts for the construction to replace up to 8,200 linear feet of 36-inch asbestos cement transmission main. 

Body

DISCUSSION:

The City of Napa water system provides potable water to 86,906 persons throughout City of Napa and unincorporated Napa County. On the western side of the city, potable water is transported from the Barwick Jamieson Treatment Plant through a 36-inch asbestos-cement (AC) transmission main to the City of Napa service area.  The 36-inch AC transmission main was installed in 1968 and is only 56 years old. Typically, an AC main would have a 100-year service life.  

 

On January 16, 2025, the City Manager determined that the 36-inch AC main replacement requires immediate action to resolve an emergency and authorized the Utilities Director to execute emergency contracts. On January 21, 2025, City Council adopted a Resolution and determined there is a need to continue the emergency action. 

 

The City posted the Request for Proposals on a Design Build contract on Friday, January 17, 2025 and held the pre-bid job walk on Thursday, January 23. The City received three proposals on February 13, 2025.

 

The City evaluated the proposals and determined Azul Works, Inc (Azul). will provide the best value for the City at a contract price of $15,725,800 with a contingency for specialty construction inspection in the amount up to 5% or $800,000 and scheduled project completion in late October 2025.   The contract with Azul was executed on March 26, 2025 and notice to proceed for the design was issued on March 27, 2025.

 

The project specifies installation of mortar lined and coated welded steel pipe for the critical transmission main requiring interim project milestones be accomplished and total project completion in 152 working days.  The current lead time for pipe procurement is 12 weeks and 24 weeks for 36-inch valves, specialty fittings and bends.

 

Azul Works, Inc has begun preliminary design activities. These include surveying, a geotechnical investigation and potholing of existing utilities along the length of the existing pipeline alignment. The preliminary activities are expected to be completed the week of April 11, 2025.

 

FINANCIAL IMPACTS:

Funds in the amount of $17,000,000 are available in CIP budget account 53160139-63WT25UTER for this project. The contract with Azul Works, Inc is valued at $15,725,800 with a contingency for specialty construction inspection in the amount up to 5% or $800,000 for a total contract price of $16,525,800.

 

CEQA:

City staff recommends that the City Council determine that the Recommended Action is exempt from CEQA pursuant to: CEQA Guidelines Section 15269 (Statutory exemption for emergency repairs, in accordance with California Public Resources Code Section 21080(b)(2)); CEQA Guidelines Section 15301 (Categorical exemption Class 1 Existing Facilities), which exempts repair, maintenance, or minor alteration of existing facilities involving negligible or no expansion of use; and CEQA Guidelines Section 15302 (Categorical Exemption Class 2 Replacement or Reconstruction), which exempts replacement or reconstruction of existing facilities on the same site and with the same purpose.

 