To: Honorable Mayor and Members of City Council
From: Julie Lucido, Public Works Director
Prepared By: John Ferons, Senior Civil Engineer
TITLE:
Title
Emergency Repair of Browns Valley Creek Damage to Browns Valley Road at Valley Glen Lane
LABEL
RECOMMENDED ACTION:
Recommendation
Determine there is a need to continue the emergency action to execute and implement contracts for the design, permitting and construction of the creek bank and sidewalk repairs adjacent to Browns Valley Creek at Browns Valley Road and Valley Glen Lane, and determine that the actions authorized by this item are exempt from CEQA.
Body
DISCUSSION:
Pursuant to City of Napa Municipal Code 2.91.040, City Staff shall continue to make reports to City Council at each regularly scheduled City Council meeting until the emergency action is terminated by the City Council. City Council heard an Administrative Report at the March 5, 2019, Council meeting and determined the need to continue the emergency.
Based on the initial evaluation by Public Works Engineering staff of the impact of the bank erosion on the adjacent sidewalk, and the potential future impact on Browns Valley Road, on February 20, 2019, the City Manager declared an emergency need to take immediate action to fund the design, permitting and construction of the repair. Engineering staff has contacted an engineering and environmental specialist to assist with necessary design and permitting for that short-term emergency engineering repair, as well as the long-term bank stabilization that is anticipated to be required.
Update: This project is continuing while the contractor wraps up punch list and paving items. Browns Valley Road is now open to both vehicles and pedestrians. The creek bank repair and wall construction is complete. Per the regulatory permits, the restoration planting is scheduled to occur in November after the seasonal rains begin.
Next steps include: Staff have determined the restoration planting is ...
Click here for full text