File #: 51-2022    Version: 1 Name:
Type: Consent Calendar Status: Passed
File created: 2/9/2022 In control: CITY COUNCIL OF THE CITY OF NAPA
On agenda: 3/15/2022 Final action: 3/15/2022
Title: Emergency Replacement of Oak Street Storm Drain
To: Honorable Mayor and Members of City Council

From: Julie Lucido, Public Works Director

Prepared By: Tim Wood, Senior Civil Engineer

TITLE:
Title
Emergency Replacement of Oak Street Storm Drain

LABEL
RECOMMENDED ACTION:
Recommendation

Determine there is a need to continue the emergency action to execute and implement construction contracts for the replacement of the Oak Street Storm Drain from Franklin Street to Brown Street, and determine that the actions authorized by this item are exempt from CEQA.

Body
DISCUSSION:
Based on the initial evaluation by Public Works engineering staff of the severe damage to the Oak Street Storm Drain and the need to replace the storm drain pipe prior to heavy winter rains, on August 25, 2021, the City Manager determined that the Oak Street Storm Drain replacement required immediate action to resolve an emergency and authorized the Public Works Director to execute emergency contracts.

Pursuant to City of Napa Municipal Code Section 2.91.040, City Staff shall make reports to City Council at each regularly scheduled City Council meeting until the emergency action is terminated by the City Council. City staff has complied with this obligation by seeking and obtaining City Council approval to continue the emergency work at each regular meeting since the City Manager's determination, including an initial administrative report on September 7, 2021, and the most recent prior Council action on March 1, 2022, to continue the emergency.

Update: The storm drain replacement for the project has been completed. As of March 3, 2022, the contractor has one concrete curb ramp and trench paving to complete the contract work. It is anticipated that all "punch list items" will be complete by the end of the month. Project close out with final accounting will be completed by end of April.

FINANCIAL IMPACTS:
Damage to the Oak Street Storm Drain was identified prior to the adoption of the current CIP budget and funding for the r...

Click here for full text